Pierre City Commissioners Approve Change Order On Street Shop Building

Pierre City Commissions approved a change order and final payment on a new building for the Street Department. Kyle Kurth with the City Engineering Department says the buildings final design for framing around overhead garage doors was not in place when the project was bid…

Commissioner Jamie Huizenga says the building is quite the improvement…

The City was able to save some money by using some existing materials…

The cost of the change order approved by Commissioners is 13-hundred 56-dollars with 726 of that for materials and the remaining 630-dollars for labor costs.